1. Northeast Trail - Segment 3 and Connector Trails

Northeast Trail - Segment 3 and Connector Trails: This federally funded portion of trail includes the mainline trail of the Atlanta Beltline 22-mile loop, called Northeast Trail – Segment 3, as well as connector trails to MARTA Lindbergh Center station, PATH 400, and to the Armour-Ottley district. The $25M RAISE Grant agreement was executed in January, and GDOT issued a notice to proceed to the Beltline. This is a long and complex project, one of the Beltline’s largest, and the expected construction duration will be 42 months.