Construction
Northeast Trail-Segment 3
The future third segment of the Northeast Trail will consist of 2.4-miles of mainline trail from Buford Highway to MARTA Lindbergh Station. It will include connections to the Armour-Ottley commercial district, the PATH400 trail, and access points from public streets. The project will involve crossings of existing MARTA heavy rail, Norfolk Southern Railway freight rail, CSX freight rail, GDOT freeway, and Peachtree Creek.
This segment of the Atlanta Beltline is not currently open to the public as there is no existing unpaved trail for use.
Project Status
The project is in the right-of-way acquisition phase. Coordination and negotiation with property owners is the primary effort now. We expect to have all land deals closed this calendar year (2024). The next major milestone is the Final Field Plan Review (FFPR) meeting this summer, which happens at about 90% design. The FFPR package was submitted to GDOT in mid-June. We are on schedule to open construction bids in summer 2025.
Project Timeline
July 2020: Approved GDOT Concept Report
July 2021: Locally Preferred Alternative announced
June 2023: Awarded a $25 million USDOT RAISE grant
March 2024: Scheduled to Complete 90% Drawings
May 2025: Target Construction Letting / Bidding
August 2025: Current Expected Construction Start