Northwest Trail-Segment 1
This section of trail is 0.8 miles in length, beginning at the western edge of Peachtree Park Apartments and running south along Peachtree Creek to Kinsey Court.

This segment is closed for construction. Trespassing on active construction sites is prohibited.




The full Northwest Trail will run for 4.3 miles from the terminus of the Westside Trail to the beginning of the Northeast Trail.
Project Status
The entire segment is now under construction. Retaining walls are 90% complete and the underground storm is also 90% complete. We are beginning to fine-grade the trail on the apartment side of the creek and will make our first trail pour at the beginning of June. The bridge superstructure is completed, and we are starting the elevated trail foundations on the north side of the creek. The project is targeting completion in June of 2026.
Project Timeline
June 2022: Survey work began.
August 2022: Prioritized alignment announced for the Northwest Trail.
October 2022: Survey work completed.
January 2023: 60% design completed.
October 2023: Reeves Young hired as Construction Manager at Risk.
January 2024: 90% drawings completed.
May 2024: Reeves Young began construction activities.
Fall 2024: Full construction began.
June 2026: Target completion date.