Skip to content

Atlanta Beltline Design and Construction Updates: July 2024

Below you will find recent updates and photos of each of our Atlanta Beltline projects in design or construction for July 2024.

  • Design & Construction
  • Parks & Trails
AUGUST 05, 2024

Below you will find recent updates and photos of each of our Atlanta Beltline projects in design or construction along with links to get more general information about each project. Additionally, you can explore current design and construction projects here. These projects play a pivotal role in furthering the Atlanta Beltline vision to be the catalyst for making Atlanta a global beacon for equitable, inclusive, and sustainable city life.

Northeast Trail

  • Northeast Trail – Segment 1: Construction is underway on this segment that runs alongside Piedmont Park and will be completed in three phases: Phase I from Westminster Drive to Evelyn Street, Phase II from Evelyn Street to Monroe Drive, and Phase III including the 10th Street and Monroe Drive intersection improvements.

    • Phase I is open with temporary fencing; final handrail installation to replace the construction fencing is in progress. Planting is complete.  The construction team is currently refurbishing the wooden Clear Creek bridge along the gravel rail trail.  Wood materials have arrived on site for the new decking.  Once the bridge is repaired, a new plaza will be poured at the head of the trail adjacent to the crosswalk.

    • Along Phase II, construction grading and wall work is ongoing within the corridor with granite cladding underway.  Concrete slab pours for the new trail are in progress, with approximately half of the trail poured to date. A new stair connection at the Piedmont Park dog park, and a ramp connecting to the sidewalks around the Six Springs Wetland area of the park, are both in progress.

    • Phase III work, which includes pedestrian safety improvements at the intersection of 10th and Monroe Drive is underway.  Key improvements include a new 10th Street bike lane providing direct access to the Atlanta Beltline to enhance connectivity and safety for trail users, a raised pedestrian crossing to improve safety for trail users and pedestrians, improved crossings and pedestrian signals at key intersections to ensure safer travel for all users of the trail, and new traffic signals at Kanuga St NE and Monroe Dr. NE to manage traffic flow and enhance safety. The full intersection closure is complete. Single-lane closures will be implemented to finalize sidewalk construction, which is expected to be complete by September 2024.  Work in progress includes the reconstruction of each corner of the intersection.  The final asphalt topping to align the road with the new curbs and stripping will complete the intersection work.  Click here for more information. 

    • The Beltline continues to work alongside Piedmont Park Conservancy, City of Atlanta Parks Department, and Atlanta Department of Transportation on this project. The project is expected to be complete in fall of 2024.

Conduit installation for lighting and cameras in Phase II of the project.

Railing installation underway along Phase I, also called the Carriage Trail through Piedmont Park.

View of improvements in progress at the intersection of Monroe Drive and 10th Street. New traffic signals are included as a part of this project (brown pole.)

Enlarged pedestrian gathering area at the intersection of Monroe Drive and 10th Street. The curb has been moved out to widen the area.

As a part of the project, the existing Eastside Trail coming into the intersection of Monroe Drive and 10th Street will be realigned with the new section of trail running through Piedmont Park.

View of completed trail work, with light and camera installation in progress as well as final grading and grassing.

The curved trail connection between Phase 1 and Phase II is now complete and also ties into the gravel rail trail.

  • Northeast Trail – Segment 2: Later this summer, the skirts (protective covers) on the lighting along the trail will be changed out for a taller and more robust style.  Additional cameras are being installed under I-75/85 and along Montgomery Ferry Road.  Selig will set the opening date for the connecting bridge to Ansley Mall, once they complete renovations to their building next to the bridge. Ansley Golf has completed netting installation.  Trees Atlanta is developing a cost and schedule to restore the meadow area disturbed by the netting installation, with all costs to be paid by Ansley Golf.

  • Northeast Trail – Segment 3: This federally funded portion of trail includes the mainline trail of the Atlanta Beltline 22-mile loop, called Northeast Trail – Segment 3, and includes connector trails to MARTA Lindberg station, PATH 400, and to the Armour-Ottley business district.  The project is in the right-of-way acquisition phase.  Coordination and negotiation with property owners is the primary effort underway.  We expect to have all land deals closed this calendar year (2024).  The next major milestone is the Final Field Plan Review (FFPR) meeting this summer, which happens at about 90% design.  The FFPR package was submitted to GDOT in mid-June.  We are on schedule to open construction bids in summer 2025.

    • Details on each Northeast Trail segment can be found in our design and construction updates section: Segment 1 and Segment 3.

Eastside Trail

  • Ponce de Leon Avenue Streetscapes: The Ponce streetscape project will provide an improved pedestrian and bicycle connection along Ponce de Leon Avenue to the Beltline running from Boulevard to Freedom Parkway. We have completed the sidewalk reconstruction, landscaping, and light pole installation throughout the project. All mast arms have been installed and the contractor is currently working with ATLDOT and Georgia Power to switch over all traffic signal operations to the new signal heads and remove the old strain pole assemblies. Bike lane improvements are complete along with pavement striping and roadway sign installation. GDOT has approved the wall and materials submittals, and the contractor will begin construction on the ramp access once the wall fabrication is complete at the end of August.

  • Updates are posted at www.beltline.org//learn/current-projects/ponce-streetscape.

    View the Beltline of streetscape improvements looking south.

    Pedestrian lighting and trees have been installed on the streetscape project.

    New bike lanes are complete and striped.

    View of streetscape improvements looking north.

    New intersection improvements including new traffic signals. Cable hung traffic lights in the photo will be removed.

Southside Trail

  • Southside Trail – Segments 2 – 3: This trail segment is 1.9 miles and runs from McDaniel to Boulevard. A contract has been executed with Reeves Young, and a Notice to Proceed was issued by ABI on April 29, 2024.  Construction mobilization started on May 20th. To protect tri-colored bat breeding habitat, federal restrictions on clearing were in place through July 31st.  Now that this restriction has passed, tree clearing, and erosion control work will begin the week of August 5th. The contractor is tightening up the security of the project in anticipation of heavy equipment related work starting next week.  This project achieved the highest level of federal funding possible at 80% of the total construction budget.  ABI anticipates having the trail construction wrapped by early 2026, to be followed by landscaping. Read more about how the acceleration of this trails segment, here

  • Southside Trail – Segments 4 – 5:  This trail segment runs from Boulevard to Glenwood and is 1.2 miles long.   Storm line installation is ongoing. Work on the Ormewood Avenue bridge abutment, south side, will continue through August. The United Avenue ramp construction is underway. Construction is continuing on the walls which will support the ramp up to Delmar. Cladding is in progress on the United Avenue bridge abutment walls.  Underground utility challenges at United Ave have pushed out the expected completion date, with construction expected to continue through fall 2025.  Detour options can be found here.

    Mechanically stabilized earth (MSE) precast panel installation, and new abuttment in progress for the new pedestrian bridge crossing at Ormwood Ave SE.

    View from Bern Street SE bridge looking north towards Glenwood Ave SE

    View from Bern Street SE bridge looking north south towards Ormwood Ave SE.

    Granite cladding underway on the abutments for the new pedestrian bridge at United Ave SE.

    Pedestrian bridge under construction at United Ave SE.

  • Southside Trail – Segment 6, Phase II:  This project will replace the interim condition and includes a new pedestrian bridge over I-20, running parallel to the existing vehicular bridge at Bill Kennedy Way.  The trail section running through Glenwood Park will also be improved to meet Beltline trail standards.  The design of this project was kicked off with the community during an ABI Study Group meeting on March 25th.  The engineering team is currently developing typical cross sections and options for street and trail composition and alignment.  A Study Group meeting will be scheduled this summer when the concepts are ready to be presented.  The project will be completed in two sections: Phase B will include work in the ATDOT right of way, which is expected to start in summer of 2025, followed by Phase A work in the GDOT right of way in summer of 2026. Details on each Southside Trail - Segment 6 can be found in our design and construction updates section, here.

Westside Trail

  • Westside Trail – Segment 4: This 1.3-mile segment begins at the current Westside Trail terminus near Lena Street and Washington Park and extends north to Law Street where the trail ties into the Westside Beltline Connector and the completed Westside Trail – Segment 3. Steel has now been placed on all five bridges, or elevated trail sections and on four of the bridges concrete has now been poured. Stone is being installed under bridges and final grading is taking place between Washington Park and Washington Manor. The fiber duct bank is complete from Lena to Washington Manor and will be progressing to Mason Turner.  We are also working on duct bank and grading along the portion of the trail on historic rail bed, also called the Kudzu Trail.  The trail has been paved from Lena to the first elevated section of trail.  Handrail installation on two of the bridges is underway. The stone walls at Donald Lee Hollowell underpass are underway. All walls have been poured.  This project is expected to be complete in summer of 2025.

    Installing rip rap along the trail edge for a drainage swale.

    View of road construction to realign the cul de sac traffic at Washington Manor Dr NW, allowing the trail to be installed where the road is currently located.

    New cul de sac curb and gutter, with trail aligned to the left of the photo and ultimately running down what is currently Washington Manor Dr NW.

    Access ramp rebar and formwork underway for concrete placement.  The ramp will provide access to the southern side of Donald Lee Hollowell Pkw NW.

    Access ramp granite cladding in progress.  This ramp will provide access to the north side of Donald Lee Hollowell Pkwy NW.

    Section of trail nearing completion along the Washington Park Tennis Center.  Lighting and camera work is in progress.

  • Ralph David Abernathy Access Point (at Westview): This project will provide a new access point to the Westside Trail, with a protected crossing across Ralph David Abernathy and a ramp and stair connection to the Beltline. A landscaped plaza is also part of the design.  Granite facing is underway on all walls. Final rough grading at top of plaza in progress, and structural soil has been installed for plaza area.  Granite pavers are underway at the entrance plaza. Pole bases are set for pedestrian lighting and cameras for the site.  The project end date is targeted for later this summer, with final landscaping to occur in early October 2024 to ensure plant survivability.

    Ramp concrete work is complete, with stainless steel railing inbeds reading for railing installation.

    Granite plaza construction in progress.

    View of ramp looking towards the Westside Beltline.

  • Ralph David Abernathy Complete Streets: This is a streetscape improvement project in the heart of the Westview business district. The project is approximately 800 feet in length and includes parking and protected bicycle lanes. All new granite curbs, sidewalks, underground storm sewer, underground electrical and pole bases are complete from East Ontario to Willard Avenue. Milling and paving from East Ontario to just past Lucile is complete and new bike lane medians are in progress with striping to follow. Removal of asphalt in planters is in progress.  The project end date is targeted for later this summer, with final landscaping to occur in early October 2024 to ensure plant survivability.

    Curbing is complete for new protected bike lanes along the business district at Ralph David Abernathy.

    Removal of asphalt within new islands protecting dedicated bike lanes.

Enota Park

  • Enota Park is an eight-acre park that will be built on the west side of Atlanta.  A contract was executed for a Construction Manager for Enota Park, and the award went to Reeves Young. ABI is working with the City of Atlanta to address revisions to real estate parcels within the park and finalizing construction permitting.  Construction is funded and targeted to start in fall of 2024. The project construction schedule is expected to be around 16 months, with an anticipated start date dependent upon permitting.

Northwest Trail

  • Northwest Trail – Segment 1:  This section of trail is 0.8 miles in length, beginning at the western edge of Peachtree Parks Apartments and running south along Peachtree Creek. We have executed a contract with Reeves Young to be our Construction Manager at Risk. Although the contractor has not physically mobilized, construction work is underway. We have begun to procure various parts of the project such as the bridge over Peachtree Creek as well as the materials for the retaining walls along the corridor and all elevated trail sections. The acquisition of easements is ongoing and once complete, we will start at the Peachtree Park Apartment complex at the beginning of Q3.

  • Northwest Trail – Segment 2: This segment begins at the southwest corner of Bobby Jones Golf Course and travels east along Colonial Hills Circle for 0.7 miles. The design drawings are 60% complete. Achieving this milestone allows real estate purchases and easements to begin.  The drawings are expected to 90% complete in September.

  • Northwest Trail – Segment 3: This section of trail begins at Trabert Avenue near Monday Night Brewing’s parking lot and ends after crossing under I-75 at Tanyard Creek, for a total length of 1.2 miles. Design will be 60% complete by the end of May 2024. A contract has been awarded to Astra Group for Construction Manager at Risk Services. The construction manager will provide early assistance with construction logistics, scheduling, and budgeting while the drawings are being completed. The section of the trail between Trabert and Northside has started construction. Storm water piping has been completed and sewer is commencing.

  • Northwest Trail – Segment 4:  This 0.9-mile-long trail begins at English and Culpepper and ends at the parking lot of Monday Night Brewery at Trabert. The 60% drawings are complete which releases real estate to begin property purchases and easements. Coordination with the Department of Watershed Management and other property owners has been very productive and the alignment for this segment has been confirmed. We will be splitting Segment 4 into two parts called Section 1 and Section 2.  We are currently soliciting a construction manager for Section 1 from English Street to Howell Mill.

  • Northwest Trail – Segment 5: This trail section begins at the intersection of Marietta Blvd and Huff Rd, traveling to Ellsworth Industrial and English Street for a total of 0.7 miles. Real estate work is complete.  The construction contract for this segment has been signed and the Notice to Proceed was issued on May 20th, 2024. The project is under construction and the contractor is completing survey work, to be followed by clearing and grubbing in the next 2-3 weeks.

Beltline Transit Study

  • This planning project, primarily focused on determining a preferred transit alignment in the NW Beltline quadrant where there is no abandoned railroad corridor, also intends to identify stop locations and generalized cross-sections in the SW and SE quadrants of the Beltline corridor. The overall study area is looking at 13-14 miles of future light-rail/streetcar transit corridor, tying into the NE Beltline quadrant planning work previously performed by MARTA in 2021. The effort is guided by principles of equity and the goal of developing a world-class network of high-capacity transit in a green guideway wherever possible.

  • Since the October 2nd kick-off meeting, we have been coordinating outreach with the community via multiple forums, including the State of the Beltline, an Equity Stakeholder Committee, 3 small-group roundtables, multiple Pop-Up engagements on weekends, etc. We expect to have sufficient information for another public meeting this summer.

  • The project will be supportive of the concept of infill stations that was announced by Mayor Dickens in April 2024. The study does not have any work started on this front yet.

  • A public meeting, providing updates on the study progress, is targeted for fall of 2024.

You can view June's Design and Construction updates here. Our second Quarterly Briefing of 2024 was held virtually on June 12, 2024. You can watch the meeting on the Atlanta Beltline's YouTube channel. 

SHARE:

Subscribe to In The Loop, our monthly newsletter, for Beltline news, events, announcements and more.

Subscribe