Southside Trail-Segments 4 and 5

Spanning 1.2 miles from Boulevard to Glenwood Avenue, the project involves a 14-foot-wide multi-use path with 3-foot soft shoulders on each side, with retaining walls, vertical connections to adjoining streets, storm drainage, replaced bridges, and more infrastructure.

Southside Trail - Segment 5 construction on the new pedestrian bridge over Ormewood Avenue. Photo by LoKnows Drones.

These segments of the Atlanta Beltline are closed for construction through Fall 2025.

Project Status

Storm line installation is ongoing. Work on the Ormewood Avenue bridge abutment, south side, will continue into mid-July. The United Avenue ramp construction will begin in mid-July and continue for the next several weeks. The trail will remain closed for the duration of construction which is expected to last through Fall 2025.

Project Timeline

  • June 2023: Construction Mobilization

  • Fall 2025: Construction Completion

Construction on the new Beltline bridge over United Avenue on Southside Trail - Segment 4. Photo by LoKnows Drones.

Design & Construction Team

  • logo for Kimley-Horn

Questions?

Nancy Newell, PE
Project Manager