Big things are happening on the Atlanta BeltLine! In addition to over seven miles of completed trail segments, there is active construction work on the BeltLine, and several segments are in various planning and design stages. Explore design and construction projects in progress.
Map View
List View
Project Name | Location | Description | Subarea |
---|---|---|---|
Northeast Trail – Segments 3, 4, 5, 6 (North) | Buford Highway to MARTA Lindbergh Station | This project will design, bid out, and build 2.4-miles of mainline trail from Buford Highway to... | 6, 7 |
Westside Trail – 1385 Ralph David Abernathy Access Point | Westside Trail near Ralph David Abernathy Blvd | The aim of this project is to provide an access point to the Westside Trail at Ralph David... | 1 |
Southside Trail – Segments 2, 3, 4, 5 | I-75 Underpass to Bill Kennedy Way | The project includes the design of a 14 foot wide concrete multi-use path and extending... | 2, 3 |
Northwest Corridor – Beltline Feasibility Study | CSX Freight Corridor – Huff to Armour Rail and NS from Howell Mill to Armour Rail | Completing the Northwest BeltLine is a key objective for the Atlanta BelLine, and will close the... | 6, 7, 8, 9, 10 |
Eastside Trail – Capital Improvements Project | Monroe to Irwin | The Atlanta BeltLine welcomes more than 2 million users a year, many of which frequent the... | 5, 6 |
Eastside – Ponce Streetscape Project | Ponce De Leon Avenue from Boulevard to Freedom Parkway | The streetscaping of State Road 8 (Ponce De Leon Avenue) will extend from Boulevard/Monroe Drive... | 6 |
Southside Trail – Brownfield Remediation | Terminus of SST-W at Pittsburgh Yards to Boulevard SE (Possibly extending to Glenwood) | ABI was awarded a $500,000 Brownfield Cleanup Grant from the Environmental Protection Agency... | 2 |
Southside – Bill Kennedy Way Interim Trail + Streetscape | Bill Kennedy Way through Glenwood Park to Glenwood Ave | This project includes improvements to the existing Bill Kennedy Way (BKW) bridge over I-20 and... | 4, 5 |
Northeast Trail – Segment 1 (Piedmont Park) | Piedmont Park (Monroe Drive to Westminster Drive) | Alternatives analysis and concept validation is underway as part of federally funded trail... | 6 |
Westside – Enota Park | Enota Park located adjacent to the Westside Trail in the Westview neighborhood | Enota Park is a +/- 8-acre park comprised of three parcels – identified as the Upper, Middle,... | 1 |
Southside – Boulevard Crossing Park | +/- 25-acre park located at the intersection of Boulevard and Englewood SE | This is Phase II of the design of Boulevard Crossing Park. The first phase of the park, which... | 3 |
Westside – Connector Trail + BeltLine Trail Segment 3 (Marietta Blvd) | PATH Trail that will connect downtown Atlanta to the Westside Beltline | The Westside BeltLine Connector is a PATH Trail that will connect downtown Atlanta to the... | 10 |
Southside Trail – Segment 1 (West Segment) | Terminus of Westside trail at Allene Ave to Pittsburgh Yards | Southside Trail Segment 1, also called Southside Trail West, is the first of five segments of... | 2 |
Southside Trail – Utility Coordination | Terminus of SST-W to Glenwood | For the Southside Trail Segments 2, 3, 4, and 5, ABI will begin the process of coordinating any... | 2, 3 |
Northeast Trail – Segment 2 (Central / Hairpin) | Clear Creek to Buford Highway; Subarea 6 | Current work, or Phase I, includes trail design and construction between Clear Creek/ Ansley... | 6 |
Westside Trail – Segment 4 (North Extension) | Lena Street (existing Westside Trail terminus) to Wheeler Street (tying into the BeltLine Connector Trail); Subareas 9 and 10 | The northern extension of the Westside Trail, also called Westside Segment 4, begins at the... | 9, 10 |
Westside – Ralph David Abernathy – Streetscape | 800’ length of streetscape and parking protected bike lanes | 10 |