Under Construction

THE ENTIRE NORTHEAST TRAIL IS NOT YET OPEN. When complete, the Northeast Trail will connect the northern end of the Eastside Trail up to the Lindbergh MARTA station. However, only a 0.8-mile stretch is open to the public in an interim state on the eastern edge of Piedmont Park. In its interim state, the trail has a rough and bumpy surface of compacted railroad gravel and dirt.

Northeast Trail

Building Connections and Critical Transit Links

Interim Trails: Rules of Use

As part of the emerging Atlanta BeltLine trail system, interim trails are accessible to the public in their unfinished state until funding is available to build out these sections of the corridor. Please note that visitors must follow the rules of use.

The Interim Tails have no additional lighting, no pavement and limited points of access. Visitors can enjoy these pleasant retreats at their own risk and are encouraged to wear appropriate footwear or use a bicycle that can handle rough terrain. Atlanta BeltLine, Inc. is not liable for any injury or damage as a result of using these unfinished trails.

Design & Construction Update

The design of the Northeast Trail is divided into three segments:

Monroe Dr. to Westminster Dr.
This section of the Northeast Trail runs between Monroe Drive and Westminster Drive. This segment, alongside Piedmont Park, will have multi-use trail in the railroad corridor. Transit will run parallel to the trail for this mile segment. Design is underway and expected to take 12-18 months to complete.

Westminster Dr. to Mayson St.
This segment, between Westminster Drive and Mayson Street, will feature transit parallel to trail. It is being designed now and constructed separately from the other two sections because of active construction by Georgia Power to replace transmission lines along this stretch. It is currently closed to the public. Installation of new utility poles and line work is complete. Between Ansley Mall and the Buford-Spring Connector, Georgia Power will be paving the Atlanta BeltLine multi-use trail, which will include the 14-foot wide trail, an access point at Montgomery Ferry Drive, stormwater systems, retaining walls, and initial landscaping. Once Georgia Power has completed their work, ABI will do follow-on work between Westminster Drive and Mayson Street to complete the full trail build-out, assuming funding is identified. This will include lighting, security cameras, landscaping, and connections to Westminster Avenue, Piedmont Avenue, and Mayson Street.

Mayson St. to MARTA Lindbergh
This section runs between Mayson Street and the Lindbergh MARTA station and faces several design challenges, including navigating active rail and I-85. For this approximately 2-mile segment, transit will diverge from the trail and the designs for both are underway. This is where the Atlanta BeltLine will intersect with Path400 and the Peachtree Creek Greenway. Because of the complicated nature of this segment and the funding mechanism, design will take 24-30 months to complete. A Locally Preferred Alternative is expected by fall 2019. View the Northeast Trail design community presentation from June 25, 2019 with updates. View the proposed Northeast Trail routes. Two alternatives have been advanced: concepts B and E. Please stay tuned for more information as we engage the public in the process.