Design

Southside Trail – Segments 2, 3, 4, 5

I-75 Underpass to Bill Kennedy Way // Subarea 2, 3

The project includes the design of a 14 foot wide concrete multi-use path and extending approximately 3.1 miles from the paved trail at Pittsburgh Yards (near the I-75 underpass) to the end of the unpaved Southside Trail at Bill Kennedy Way. Southside Trail – Segments 2 and 3 make up 1.9 miles and Segments 4 and 5 are 1.2 miles.

Additional site elements include planting, lighting, retaining walls, vertical connections to adjoining streets, storm drainage, signage/wayfinding, and the replacement and rehabilitation of several bridges. The design also includes streetscape/accessibility improvements on all intersecting streets extending from the corridor to the nearest intersection or one-quarter mile, whichever was closest.

ABI was awarded a $500,000 Brownfield Cleanup Grant from the Environmental Protection Agency (EPA). Grant funds will be used to clean up portions of the interim Southside Trail. Soil remediation will focus on 26 areas as identified in the Analysis of Brownfield Cleanup Alternatives (ABCA) previously prepared by United Consulting. The Analysis of Brownfield Cleanup Alternatives (ABCA) is available for viewing here. The report, part of an EPA grant, provides information about any contamination found on site and alternatives for cleaning up any the contamination.

Southside Trail design and construction status June 2023
Southside Trail design and construction status as of June 2023.

Project Status

The Southside Trail has project has been broken into six segments.

  • Southside Trail – Segments 2 – 3: Construction bids were received on February 27th and a low bidder has been approved by ABI, GDOT, and FHWA.  The team is working to mobilize and start construction in late spring of 2024.  If construction starts as planned, ABI anticipates to have the trail construction wrapped by early 2026, to be followed by landscaping. This project achieved the highest level of federal funding possible at 80% of the total construction budget.  On the interim trail, rail events have caused slope failure along Skylark Apartments.  A temporary engineering fix has been developed to stabilize the condition near term.  A permanent stabilization solution will be implemented as a part of the construction work.  Trail users should use caution around these areas, which are restricted with cones and barriers.
  • Southside Trail – Segments 4 – 5:  Storm line installation is ongoing. The contractor is working at the United Avenue bridge and expects to have the new abutments constructed and begin setting beams by the end of April. Grading prep for the United Avenue ramp will begin mid-April and continue throughout the end of May. Pile driving for bridge abutments at Ormewood Avenue will begin the last week of April. Reeves Young will also be continuing construction on the walls which will support the ramp up to Delmar throughout May. The trail will remain closed for the duration of construction which is expected to last through spring 2025. Detour options can be found here.
  • Manford Road Streetscapes: This project includes the construction of connecting sidewalks to the Southside Trail from the Capitol View Manor neighborhood.  Contractor has constructed the walls, ADA ramps, crosswalks, and signage. Sidewalk construction should be fully completed by mid-April.
Atlanta BeltLine Southside Trail detour option between Glenwood Avenue and Boulevard.
Atlanta BeltLine Southside Trail detour option between Glenwood Avenue and Boulevard.
Atlanta BeltLine Southside Trail detour option from United Avenue access point.
Atlanta BeltLine Southside Trail detour option from United Avenue access point.
Atlanta BeltLine Southside Trail detour option from the west side of the Mercer Street access point.
Atlanta BeltLine Southside Trail detour option from the west side of the Mercer Street access point.
Atlanta BeltLine Southside Trail detour option from the east side of the Mercer Street access point.
Atlanta BeltLine Southside Trail detour option from the east side of the Mercer Street access point.

Project Timeline

March 2018
The City of Atlanta and ABI purchased the southside corridor, representing more than 4 miles and 63 acres
August 2019
The Southside Trail opened for public use in an unpaved condition
July 2020
Emergency demolition of bridge over United Avenue
May 2021
Interim safety improvements along Bill Kennedy Way (Southside Trail - Segment 6) completed
May 2021
ABI awarded $4 million in grant funding from the Atlanta Regional Commission
November 2021
RAISE grant awarded for $16.46 million towards construction
August 2022
Brownfield remediation work completed by Reeves Young
August 2022
Invitation to Bid posted for construction of Segments 4 and 5
2022-early 2023
Utility relocation and remediation work
May 2023
Construction began on Segments 4 and 5
December 2023
Segment 2 and 3 will be released for big for construction
Spring 2024
Goal to begin trail construction on Segments 2 and 3
Early 2026
Anticipated completion of trail Segments 2 and 3
Spring 2025
Segments 4 and 5 closed through construction

Last Updated: April 1, 2024