Atlanta Beltline Design and Construction Updates: June 2025
Below you will find recent updates and photos of each of our Atlanta Beltline projects in design or construction for June 2025.
Design & Construction
Parks & Trails
Transit
JULY 01, 2025
Below you will find recent updates and photos of each of our Atlanta Beltline projects in design or construction along with links to get more general information about each project. Additionally, you canexplore current design and construction projects here. These projects play a pivotal role in furthering the Atlanta Beltline vision to be the catalyst for making Atlanta a global beacon for equitable, inclusive, and sustainable city life.
Northeast Trail
Northeast Trail - Segment 3 and Connector Trails:This federally funded portion of trail includes the mainline trail of the Atlanta Beltline 22-mile loop, called Northeast Trail – Segment 3, as well as connector trails to the MARTA Lindberg station, PATH 400, and to the Armour-Ottley business district. All real estate has been purchased, and the design is 100% complete. This is a huge milestone which ensures that the trail can be built!GDOT has certified all review packages such as environmental, right of way (real estate), and utility relocation work. The final step is the execution of federal grant agreements which is in progress. This project has more than $42M in federal funding. We are expecting the project to be bid for construction in Q1 of 2026, or earlier, and will likely be mobilized for construction in mid-2026. This is a long and complex project, one of the Beltline’s largest, and the expected construction duration is expected to be 42 months.
Southside Trail
Southside Trail Segments 2+3:This project, which extends 1.9 miles from west of I-75/85 to Boulevard, was released for construction with a construction mobilization date of May 20th 2024, and an early 2026 completion timeline. Clean-up of the brownfield continues on Segment 3 near Milton Avenue & D.H. Stanton Park. The installation of large stormwater management systems is in progress west of Pryor Road and Milton. The Access points east of Pryor and Hill Street are in progress with grading and wall construction underway. The majority of the concrete trail is expected to be poured by mid-March of 2026. The schedule for the remaining trail to be poured, for the stretch from D.H. Stanton to Milton, is contingent upon the progress of the brownfield work in the area. ABI is working to have this trail open to the public prior to June 2026, when FIFA will be held in Atlanta.
Southside Trail Segments 4+5:This trail segment runs from Boulevard to Glenwood and is 1.2 miles long. All columns for the ramp at United are complete as well as the mechanically stabilized earth (MSE) retaining walls and backfill. The ramp system at Delmar has been completed. The underground stormwater detention chambers have been installed on the north side of Ormewood, and backfilling of the area at the bridge is in progress. A concrete bent (pedestal) for the new Ormewood Ave pedestrian bridge has been constructed, and the contractor will be working on the MSE walls for the ramp and stair structures. The first trail pour between Boulevard and United is complete, and the installation of light poles and light pole bases is underway for this section of trail. The United Avenue bridge has railing installed, and backfill to the north of the bridge is substantially complete. Granite cladding work is in progress at the MSE walls adjacent to the bridge. Underground utility challenges at United Ave have pushed out the expected completion date, with construction expected to complete by fall 2025.
Pictured from left to right: View of Ormewood Ave SE bridge construction. Historic bridge is to the left. The crew in installing a retaining wall to bring the grades up to the level of the historic and new bridge. (Photo Credit: ABI Staff)View of Ormewood Ave SE bridge construction. View of new concrete abutment to the left. Bridge structure will be added to connect this abutment to the bridge already in place across Ormewood Ave SE. (Photo Credit: ABI Staff)View of columns which will support a new curved ramp up to the trail from United Ave SE. Crews are installing scaffolding and working on granite cladding for the abutment walls. (Photo Credit: ABI Staff)View of trail from United Ave SE bridge facing north. Crews are currently raising the grade up to the final finished grade of the trail. (Photo Credit: ABI Staff)View of trail from United Ave SE bridge facing north. Crews are currently raising the grade up to the final finished grade of the trail. (Photo Credit: ABI Staff)Pictured from left to right: View looking south of trail poured from United Ave SE to Boulevard SE. View from Boulevard SE. of completed trail to United Ave SE. (Photo Credit: ABI Staff)
Southside Trail - Segment 6 (Bill Kennedy Way at I-20):This project includes a new pedestrian bridge over I-20, running parallel to the existing vehicular bridge at Bill Kennedy Way. The trail section running through Glenwood Park will also be improved to meet Beltline trail standards. The drawings for the project 60% complete. The engineering team is completing a traffic analysis that contemplates changes to adjacent streets and intersections, with the intent to minimize trail and car traffic conflicts. The project will be completed in two sections: Section A will include work in the ATLDOT right-of-way south of I-20 and Section B is the GDOT right of way from I-20 north to Memorial Drive. Consideration of how to phase this work around FIFA events in June of 2026 is needed. Expected construction duration for each phase of work is expected to be between 16-18 months.
Westside Trail
Westside Trail – Segment 4:This 1.3-mile segment begins at the current Westside Trail terminus near Lena Street and Washington Park and extends north to Law Street where the trail ties into the Westside Beltline Connector and the completed Westside Trail - Segment 3. The trail is now open to the public, and a ribbon cutting was held on Monday, June 23rd. Click here to learn more.
Westside Trail – Segment 6: This trail will be 0.6 miles in length and connects the Westside Trail at Lawton Street SW to the Westside Trail at Ralph David Abernathy Boulevard. This section of trail is open but is a sidewalk connection, diverted off the rail corridor with ramp connections to an adjacent sidewalk. This project will construct a trail connection on the rail corridor. Design has started and 30% design is expected end of September 2025.Design is expected to run through Spring of 2026 and construction to be complete by 2027. Landscaping work will extend into 2028.
Northwest Trail
Northwest Trail – Segment 1: This section of trail is 0.8 miles in length, beginning at the western edge of Peachtree Parks Apartments and running south along Peachtree Creek. The entire segment is now under construction. All tree clearing and utility relocations are complete on both sides of the creek. Retaining wall work is in progress as well as underground stormwater infrastructure work. Parking lot reconfigurations at Peachtree Park apartments is complete. The bridge superstructure is completed, with a concrete pour for the bridge expected in early July. Elevated trail foundations, columns, and bents on the north side of the creek are in progress. Trail has been poured adjacent to the first three apartment buildings. The project is targeting completion in June of 2026.
Pictured from left to right: View of elevated trail structure coming off of the Peachtree Creek bridge. Trail is elevated to minimize impacts to the trail from flooding events. (Photo Credit: ABI Staff)Soil cells are modular, underground structures used to create space for healthy tree growth in urban environments where space is limited. They provide a supportive matrix for uncompacted soil, allowing tree roots to access nutrients, water, and oxygen, while also supporting paved surfaces like sidewalks and roads. This system helps trees thrive in urban settings, mitigating issues like soil compaction and stormwater runoff. (Photo Credit: ABI Staff)View of crews installing soil into soil cells. (Photo Credit: ABI Staff)View of newly poured concrete trail adjacent to Peachtree Park Apartments. A patio and patio fencing for each apartment will ultimately be installed for apartment occupants. (Photo Credit: ABI Staff)View of completed retaining wall which will be clad in granite. The trail will run along side this wall. (Photo Credit: ABI Staff)
Northwest Trail – Segment 2:This segment begins at the southwest corner of Bobby Jones Golf Course and travels east along Colonial Hills Circle for 0.7 miles. The design drawings are complete. Real estate purchases and easement work is in progress and are expected to be wrapped up in early 2026.
Northwest Trail – Segment 3: This section of trail begins at Trabert Avenue near Monday Night Brewing’s parking lot and ends after crossing under I-75 at Tanyard Creek, for a total length of 1.2 miles. Design work is complete and permitting is in progress. The section of the trail, Section A, between Trabert and Northside is nearing completion and expected to be open for use in late June or early July.The Monday Night Brewing expansion, adjacent to the trail, is expected to open in August.We expect real estate work to be completed for Segment 3B by November of this year. The construction schedule for this 1.0-mile section of trail that runs from Northside Drive to Tanyard Creek Park, will be established later this year, after the real estate is closed.
Pictured from left to right: View of completed trail adjacent to the expansion of Monday Night Brewing in West Midtown between Trabert Ave NW and Northside Drive NW. (Photo Credit: ABI Staff)View of completed trail looking towards Northside Drive NW. The property owners of the building to the left have redevelopment plans. (Photo Credit: ABI Staff)View of completed trail looking running parallel and up to Northside Drive NW. The crew is putting the finishing touches on the concrete, including installing sealant in the concrete joints. (Photo Credit: ABI Staff)
Northwest Trail – Segment 4: This 0.9-mile-long trail begins at English and Culpepper and ends at the parking lot of Monday Night Brewery at Trabert. The drawings are complete, and we are substantially complete with required permitting. We have split Segment 4 into two parts called Section A and Section B. We have finalized the selection of a Construction Manager at Risk, F. H. Paschen, for Section A from English Street to Howell Mill. We released all steel for bridge fabrication, and demolition work is completed on Section 4A. We expect to have final pricing in place for Section 4A and to release the work to start construction by September. The schedule for the smaller Section 4B has not been confirmed, but will likely start later this year.
Northwest Trail – Segment 5:This trail section begins at the intersection of Marietta Blvd and Huff Rd, traveling to Ellsworth Industrial and English Street for a total of 0.7 miles. Construction started in May of 2024. Retaining walls and the bridge between Elaine and Fairmont are ongoing. The bridge’s concrete surface has been poured. Retaining wall work at Ellsworth into the corridor is starting to take shape. Trail grading at Fairmont and the corridor is ongoing. Most of the trail along Elaine has been poured. Discussions around the Elaine and Ellsworth intersection have started with ATLDOT for a planned road closure in July, for both the trail crossing work and intersection improvements. The retaining wall near English Ave is nearing completion. Marietta Blvd wall construction and demolition work is ongoing with minimal traffic impacts. This project is expected to be complete by October 2025.
Retaining wall construction at the intersection of Ellaine Ave and Ellsworth Industrial Blvd NW. (Photo Credit: ABI Staff)View of retaining walls supporting at future trail alignment. View looking east from Ellsworth Industrial Blvd NW adjacent to Forsyth Fabric. (Photo Credit: ABI Staff)Pictured from left to right: View looking east from Ellsworth Industrial Blvd NW towards Fairmont Ave NW. Bridge concrete has been poured. (Photo Credit: ABI Staff)View looking east from Ellsworth Industrial Blvd NW towards Fairmont Ave NW beyond bridge at creek. (Photo Credit: ABI Staff)Pictured from left to right: View looking west from Ellsworth Industrial Blvd NW up Ellaine Ave NW. Concrete trail has been poured as a side path by moving the curb on Ellaine Ave NW and narrowing the road width headed towards Marietta Blvd NW.(Photo Credit: ABI Staff)Ellsworth Industrial Blvd NW and Elaine Ave NW intersection. Intersection will be reconfigured to improve pedestrian safety where the Woodall Rail Trail and the Beltline intersect. Sawcutting of asphalt is in progress. (Photo Credit: ABI Staff)View of Marietta Blvd NW looking north towards Elaine Ave NW. Asphalt has been removed, grading is in progress, and retaining walls are complete to the left. The Beltline will run as a side path adjacent to the road with a vegetative buffer and guard rail. (Photo Credit: ABI Staff)View of Marietta Blvd NW. at completed Westside Trail 3. This is what the section of Northwest Trail 5 will look like when complete. (Photo Credit: ABI Staff)
Beltline Connector Trails + Access Points
Oakland City MARTA Station + Murphy Connector Trail: This connector trail is expected to be 1.31 miles in length in total, beginning at the existing Southside Trail access point at Allene Avenue SW and splitting into two segments. The first segment of the trail is .45 miles in length and starts at Allene Avenue SW, crosses over Sylvan Road SW, and terminates at Murphy Avenue. The second segment of the trail is .86 miles in length and starts at Allene Ave SW, runs adjacent to Avon Ave, crosses over Sylvan Road SW, crosses over Dill Ave, and terminates at Murphy Oakland City MARTA station. Solicitation of a design firm is complete, and contract execution is underway. Design is expected to run through early 2026, and construction to be complete in mid-2028. Landscaping work will extend into the winter months of 2028. This project is funded through design in the most recent Beltline Strategic Implementation Plan; construction funding has not yet been identified.
All Trails Initiatives
Signage, Wayfinding & Crosswalks: Design is complete. The design packages includes regulatory signage, wayfinding signage, and crosswalk designs. The new signage package is consistent across the entire corridor and in alignment with new ABI branding. A Construction Manager at Risk has been chosen, and contract negotiations are underway. We have submitted for permit with ATLDOT and submitted the EDI to GDOT. Construction will start on signage packages in mid-2025, with all work on completed trails targeted to wrap up prior to FIFA in June 2026.
Lighting and Camera Installations:Design is underway for the Northeast Trail gravel ‘rail trail’ and the gravel trail at Westside Trail Segment 6 to add security improvements such as lighting, cameras, and a crushed granite aggregate surface. Design for the Camera upgrades along the existing Westside Trail corridor is complete. A contractor under Beltline’s current Construction Task Order solicitation will be chosen for installation, which is currently in procurement.
Parks
Enota Park:Enota Park is an eight-acre park that will be built on the west side of Atlanta. Clearing and grading has been in progress and will continue through July. The demolition of the existing structure at Lucille will start in July. Utility coordination for the demolition of the building and for Enota Place is ongoing. The project is expected to be complete in Q3 of 2026.
Shirley C. Franklin Park (formerly Westside Park) – Mountain Bike Trail and Pump Track:This Westside Park project consists of a 2.25-mile mountain bike trail for various skill levels as well as a pump track facility for teaching the sport of mountain biking. The current program for the mountain bike trails includes 0.37 miles of beginner trails, 0.67 miles of intermediate/expert gravity trails, and 1.19 miles of intermediate bidirectional trails. The project design will also include 0.75 miles of hiking trails. ABP has recently confirmed an $8M donation, bringing the total funding raised for the project to $8.8M. This funding will cover the first phase of work, with fundraising required to complete the entire project and all desired elements and phases of work. The team is currently working to finalize pricing for the 60% Design Development Package. Developing pricing, a cost estimate, and a schedule for the first phase of work will be the focus of the design team over the next few months. Construction for the first phase of work may start in fall of this year.
Early concepts for the mountain bike trails, walking trails, and bike park.
Boulevard Crossing Park: Design work is complete for an expansion of the existing park from 5 acres to 25 acres, including a direct access path to the Southside Trail. Construction funding will need to be identified to progress the project.
Streetscapes
Ponce de Leon Ave: This project involves 0.68 miles of streetscape work along Ponce de Leon, as well as a new ramp providing access to the Eastside Trail from Ponce de Leon. Sidewalk construction, light pole installation, mast arm and traffic signal installation, bike lane resurfacing and extension, striping, and landscaping have been completed. Wall construction for the ramp and granite veneering is complete. Columns for the elevated ramp structure have been poured, the elevated structure is in place, and railing work is underway. Estimated completion date of the project is Summer 2025.
Access ramp from the Eastside Trail to Ponce De Leon Ave. Railing installation is in progress. (Photo Credit: ABI Staff)Access ramp from the Eastside Trail to Ponce De Leon Ave. Railing installation is in progress. (Photo Credit: ABI Staff)
Beltline Transit Feasibility Study
This planning project, primarily focused on determining a preferred transit alignment in the NW Beltline quadrant, where there is no abandoned railroad corridor, also intends to identify stop locations and generalized cross-sections in the SW and SE quadrants of the Beltline corridor.The overall study area is looking at 13-14 miles of future light-rail/streetcar transit corridor, tying into the NE Beltline quadrant planning work previously performed by MARTA in 2021.The effort is guided by principles of equity and the goal of developing a world-class network of high-capacity transit in a green guideway wherever possible.
The consultant team has been coordinating outreach with the community through multiple forums, including Equity Stakeholder Committee meetings, small-group roundtables, multiple Pop-Up engagements on weekends, etc.Multiple public meetings have been hosted with the community in September, October, and November of 2024, and more engagement is forthcoming.
This project is anticipated to be completed in 2025.