Construction
Westside Trail-Segment 4
This northern segment runs for about 1.3 miles, starting from the existing Westside Trail terminus at Lena Street and extending north to Law Street, where it will tie into Westside Trail—Segment 3 and the Westside Beltline Connector.
While the section between Lena Street and Mayson Turner is open, the rest of this segment is closed for construction. Trespassing on active construction sites is prohibited.
Project Status
The southern portion of Westside Trail — Segment 4 is now open to the public. This section runs from Lena Street to Mayson Turner.
Landscaping on this section of the trail is ongoing.
All six bridges have now been poured and handrail work has started.
Retaining walls have been constructed and faced with granite, including the smooth granite on the retaining wall by Donald Lee Hollowell.
Project Timeline
March 2023: Groundbreaking and Construction Began
Summer 2025: Anticipated Construction Completion