Design & Construction
Bike Park at Shirley Clarke Franklin Park
Once the project is fully funded and out of design, the Bike Park at Shirley Clarke Franklin Park will be one of the most unique and inclusive biking facilities in Atlanta, featuring 2.25 miles of mountain bike trails catering to various skill levels, a pump track, a bicycle playground, jump lines, a skills course, and hiking trails.

The Atlanta Beltline Partnership is still raising funds to complete the Bike Park, a space where riders of all ages can ride, explore, and have fun.







Shirley Clarke Franklin Park mountain bike trails user types.
Project Status
ABP has recently confirmed an $8M donation, bringing the total funding raised for the project to $9M. This funding will cover the first phase of work with fundraising required to complete the entire project and all desired elements and phases of work.
We now have the contract with the Construction Manager at Risk (Reeves Young). We have had preliminary meetings with the City of Atlanta permitting and will begin permitting after the 90% drawings are received in early August. A groundbreaking ceremony is scheduled for January 22, 2026.
Click here for the latest updates and support us in reaching our goal!
Project Timeline
February 2024: The project was presented to the Parks/WSP Advisory Board in late February.
April 2024: Survey in park for bike trails and hiking trails was flagged and took place. The team will begin more detailed layouts for pump track and skills areas.
Fall 2025: First phase of work released to start construction
January 2026: Groundbreaking is scheduled for January 22.

Meghan Injaychock
Project Manager