Design & Construction
Bike Park at Shirley Clarke Franklin Park
Once the project is fully funded and out of design, the Bike Park at Shirley Clarke Franklin Park will be one of the most unique and inclusive biking facilities in Atlanta, featuring 2.25 miles of mountain bike trails catering to various skill levels, a pump track, a bicycle playground, jump lines, a skills course, and hiking trails.








Shirley Clarke Franklin Park mountain bike trails user types.
Project Status
ABP has recently confirmed an $8M donation, bringing the total funding raided for the project to $8.8M. The project is expected to cost $15M to complete all desired elements and phases of work.
We are currently wrapping up the contract with the Construction Manager at Risk (Reeves Young) and working on edits to the 60% Design Development Package.
Developing pricing, a cost estimate and schedule for the first phase of work will be the focus of the design team over the next few months. Construction for the first phase or work may start in fall of this year.
Project Timeline
February 2024: The project was presented to the Parks/WSP Advisory Board in late February.
April 2024: Survey in park for bike trails and hiking trails was flagged and took place. The team will begin more detailed layouts for pump track and skills areas.
End of 2025: The first phase of construction is expected to begin.
Meghan Injaychock
Project Manager