Northwest Trail-Segment 5

This trail section begins at the intersection of Marietta Boulevard and Huff Road and travels 0.7 miles to Ellsworth Industrial and English Street. The project will involve building Beltline trail outside of the railroad corridor. The trail corridor follows the east side of Elaine Avenue, NW and crosses over Ellsworth Industrial Avenue, where a greenway trail starts from Ellsworth Industrial to English Street. The intersection of Ellsworth Industrial and Elaine Avenue, NW is proposed to become a three-way stop for vehicular traffic.

Green powerline corridor with Atlanta skyline in the background

This segment is currently closed for construction. Trespassing on active construction sites is prohibited.

The full Northwest Trail will run for 4.3 miles from the terminus of the Westside Trail to the beginning of the Northeast Trail.

Project Status

Construction started in May of 2024. Walls and bridge between Elaine and Fairmont are ongoing. Discussions around the Elaine and Ellsworth intersection have started with ATLDOT for full closure this summer. Elaine storm work and grading is nearing completion. Duct bank installation is nearing completion. Marietta Blvd wall construction has started with minimal traffic impacts. Bridge steel arrived and was installed for a 70’ bridge which will provide crossing over a creek. This project is expected to be complete by Fall of 2025.

Project Timeline

  • February 2024: Construction Bid Solicitation

  • April 2024: Construction contract awarded to Astra

  • May 2024: Notice to Proceed issued

  • June 2024: Groundbreaking ceremony took place

  • July 2024: Construction started with clearing and grubbing

  • October 2025: Construction complete (14-month schedule)

Green powerline corridor with Atlanta skyline in the background

Design & Construction Team

Questions?

Meghan Injaychock
Project Manager