Design
Northwest Trail-Segment 1
This section of trail is 0.8 miles in length, beginning at the western edge of Peachtree Park Apartments and running south along Peachtree Creek to Kinsey Court.

This segment is closed for construction. Trespassing on active construction sites is prohibited.




The full Northwest Trail will run for 4.3 miles from the terminus of the Westside Trail to the beginning of the Northeast Trail.
Project Status
The entire segment is now under construction. All tree clearing and utility relocations are complete on both sides of the creek. Retaining wall work is in progress as well as underground stormwater infrastructure work. Parking lot reconfigurations at Peachtree Park apartments is complete. The bridge superstructure is completed, with a concrete pour for the bridge expected in early July. Elevated trail foundations, columns, and bents on the north side of the creek are in progress. Trail has been poured adjacent to the first three apartment buildings. The project is targeting completion in June of 2026.
Project Timeline
June 2022: Survey work began.
August 2022: Prioritized alignment announced for the Northwest Trail.
October 2022: Survey work completed.
January 2023: 60% design completed.
October 2023: Reeves Young hired as Construction Manager at Risk.
January 2024: 90% drawings completed.
May 2024: Reeves Young began construction activities.
Fall 2024: Full construction began.
June 2026: Target completion date.