Northwest Trail-Segment 1
This section of trail is 0.8 miles in length, beginning at the western edge of Peachtree Parks Apartments and running south along Peachtree Creek.
This segment is closed for construction. Trespassing on active construction sites is prohibited.
Project Status
The trail on the north side of Peachtree Creek is now under construction. We have completed the tree clearing and over the next month, we will begin working on the foundations for the bridge. The bridge construction itself will begin in February.
On the south side of the creek, we have our land agreements in place and will begin construction work in January.
Project Timeline
June 2022: Survey work began.
August 2022: Prioritized alignment announced for the Northwest Trail.
October 2022: Survey work completed.
January 2023: 60% design completed.
October 2023: Reeves Young hired as Construction Manager at Risk.
January 2024: 90% drawings completed.
May 2024: Reeves Young began construction activities.
Fall 2024: Full construction began.