For the Southside Trail Segments 2, 3, 4, and 5, ABI will begin the process of coordinating any necessary utility relocations in preparation for future trail construction. All utilities that are in the path of construction work must be relocated prior to the start of construction activities. Companies that may be required to relocate their utilities might include Verizon, GDOT, GA Power, Atlanta Gas, AT&T, and Zayo.

Segment 2: Terminus of SST-W at Pittsburgh Yards to Milton Ave SE

Segment 3: Milton Ave. SE to Boulevard SE

Segment 4: Boulevart to Delmar

Segment 5: Delmar to Glenwood