Construction

Southside Trail – Segments 4, 5

Boulevard to Glenwood // Subarea 2, 3

The project includes a 14-foot-wide concrete multi-use path with 3-foot soft shoulders on each side, spanning approximately 1.2 miles from Boulevard to Glenwood.

Site elements of the finished trail will include planting, lighting, retaining walls, vertical connections to adjoining streets, storm drainage, signage/wayfinding,and  construction of new bridges at Ormwood Ave SE and United Ave. SE.

Southside Trail design and construction status June 2023
Southside Trail design and construction status as of June 2023.

Project Status

 

The United Avenue bridge deck has been poured and the contractor will be working on the additional MSE walls in June. Work for the Ormewood Avenue bridge will continue throughout June. Reeves Young will also be continuing construction on the walls which will support the ramp up to Delmar throughout June 2024.

 

 

Project Timeline

June 2023
Construction Mobilization
May 2025
Construction Completion

Last Updated: May 9, 2024