This project will design, bid out, and build 2.4-miles of mainline trail from Buford Highway to MARTA Lindbergh Station. It will include a connection with the PATH400 trail and access points from public streets. The project will involve crossings of existing MARTA heavy rail, NSR freight rail, CSX freight rail, GDOT freeway, and Peachtree Creek.
Project Status
This federally funded portion of trail includes the mainline trail of the Atlanta BeltLine 22-mile loop, called Northeast Trail – Segment 3, and also includes connector trails to MARTA Lindberg station, PATH 400, and to the Armour-Ottley business district. The design team is scheduled to complete 90% drawings by March of 2024. Real estate acquisition and construction easements are underway and will be followed by GDOT approvals for right of way, environmental, and utility work. A total of 16 real estate parcels will require agreements with property owners. Construction letting / bidding is targeted for May 2025. The current expected construction start is August of 2025, with up to a three-year schedule to complete the mainline trail and the connector trails.
Project Timeline
Last Updated: March 4, 2024