Design

Northeast Trail – Segment 1 (Piedmont Park)

Piedmont Park (Monroe Drive to Westminster Drive) // Subarea 6

The Northeast Trail – Segment 1 runs 0.9 miles alongside Piedmont Park from Monroe Drive to Westminster Drive. A Locally Preferred Alternative was announced in July 2021 as part of the federally funded, full length of the Northeast Trail design project from Monroe Drive north to MARTA Lindbergh Station.

Project Status

Design of this segment is currently underway.

Project Timeline

May 2020 - July 2021
Alternatives analysis and concept validation
July 2021
Execute contract for design phase services
September - October 2021
Gravel installation along unpaved path
February 2022
Design documents anticipated to be at 30% completion
Early 2023
Anticipated completion of design documents

Last Updated: January 27, 2022