Construction
1385 Ralph David Abernathy Access Point
The aim of this project is to provide an access point to the Westside Trail at Ralph David Abernathy Boulevard (RDA). This will include the reconfiguration of South Gordon Street NW to add crosswalks, Rectangular Rapid Flash Beacons (RRFB), and other safety improvements for pedestrians and cyclists. A landscaped plaza is also part of the design.
Project Status
Granite facing is underway on all walls and is anticipated to be complete by the first week of July. Final rough grading at top of plaza in progress, and structural soil has been installed for plaza area. Pole bases are set for pedestrian lighting and cameras for the site.
The project end date is targeted for late July, with final landscaping to occur in early October 2024 to ensure plant survivability.