Northwest Trail-Segment 1

This section of trail is 0.8 miles in length, beginning at the western edge of Peachtree Park Apartments and running south along Peachtree Creek to Kinsey Court.

Rendering of where the future Northeast and Northside Trails will meet at the end of Kinsey Court in the Peachtree Hills neighborhood.

This segment is closed for construction. Trespassing on active construction sites is prohibited.

The full Northwest Trail will run for 4.3 miles from the terminus of the Westside Trail to the beginning of the Northeast Trail.

Project Status

The entire segment is now under construction. We have completed about 80% of all concrete walls on this segment and the stormwater system is not complete. The cable stay bridge structure is in place and we will pour the bridge deck the first 2 weeks of May. We anticipate beginning to pour the trail itself on the apartment side starting the first week in June. The project is targeting completion in June of 2026.

Project Timeline
  • June 2022: Survey work began.

  • August 2022: Prioritized alignment announced for the Northwest Trail.

  • October 2022: Survey work completed.

  • January 2023: 60% design completed.

  • October 2023: Reeves Young hired as Construction Manager at Risk.

  • January 2024: 90% drawings completed.

  • May 2024: Reeves Young began construction activities.

  • Fall 2024: Full construction began.

  • June 2026: Target completion date.

Design & Construction Team

Questions?

Jay Suever
Project Manager