Northwest Trail-Segment 1

This section of trail is 0.8 miles in length, beginning at the western edge of Peachtree Parks Apartments and running south along Peachtree Creek.

Rendering of where the future Northeast and Northside Trails will meet at the end of Kinsey Court in the Peachtree Hills neighborhood.

This segment is closed for construction. Trespassing on active construction sites is prohibited.

The full Northwest Trail will run for 4.3 miles from the terminus of the Westside Trail to the beginning of the Northeast Trail.

Project Status

The trail on the north side of Peachtree Creek is now under construction. We have completed the tree clearing and over the next month, we will begin working on the foundations for the bridge. The bridge construction itself will begin in February.

On the south side of the creek, we have our land agreements in place and will begin construction work in January.

Project Timeline
  • June 2022: Survey work began.

  • August 2022: Prioritized alignment announced for the Northwest Trail.

  • October 2022: Survey work completed.

  • January 2023: 60% design completed.

  • October 2023: Reeves Young hired as Construction Manager at Risk.

  • January 2024: 90% drawings completed.

  • May 2024: Reeves Young began construction activities.

  • Fall 2024: Full construction began.

Design & Construction Team

Questions?

Jay Suever
Project Manager